Steno

Download PDF data sheet
Steno completed
Steno completed

Particulars

Owner: Ministry of Agriculture

Designer: Hydro-Systems Ltd

Contractor: Geotechniki Themeliosseon Ltd.

Statistics

Type: Hardfill

Purpose(s): Irrigation / Water Supply

Reservoir capacity: 1 m3x106

Height: 32 metres

Length: 170 metres

Volume of RCC: 69 m3x103

Total volume: 70 m3x103

Construction Dates

Start of Project: 02/00 (February 2000)

Start of RCC: 07/01 (July 2001)

End of RCC: 10/02 (October 2002)

End of Project: 06/03 (June 2003)

Country: Greece

River: Steno

DMS Co-ordinates: 37˚09'32.52"N, 24˚31'04.87"E

DD Co-ordinates: 37.159035, 24.518019

Facings

Upstream

SlopeType
0.70Reinforced concrete cast against precast units or slip-formed facing elements

Downstream

SlopeType
0.70RCC against precast concrete blocks

Spillway

SlopeType
0.70Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
200  -200  -
300300

Cementitious material

Cement (kg/m3)
55
Pozzolan (kg/m3)Pozzolan Type
5Natural pozzolan (ASTM Class N)