Lithaios

Download PDF data sheet
Lithaios under construction
Lithaios under construction

Particulars

Owner: Trikala Prefecture

Designer: Hydro-Systema Ltd

Contractor: Mattheos Techniki ATE

Statistics

Type: Hardfill

Purpose(s): Irrigation

Reservoir capacity: unknown

Height: 32 metres

Length: 526 metres

Volume of RCC: 160 m3x103

Total volume: 220 m3x103

Construction Dates

Start of Project: 06/03 (June 2003)

Start of RCC: 11/11 (November 2011)

End of RCC: 11/16 (November 2016)

End of Project: 08/18 (August 2018)

Country: Greece

River: Lithaios

DMS Co-ordinates: 39˚43'35.24"N, 21˚45'25.37"E

DD Co-ordinates: 39.726456, 21.757048

Facings

Upstream

SlopeType
0.80Reinforced concrete cast against precast units or slip-formed facing elements

Downstream

SlopeType
0.80RCC against formwork

Spillway

SlopeType
0.80Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
50
Pozzolan (kg/m3)Pozzolan Type
10Natural pozzolan (ASTM Class N)