Beni Haroun Dam
<:: Return to list
Owner:
Agence Nationale des Barrages, Algeria
Designer: Tractebel
Contractor: Dragados y Construcciones
Consultant to Contractor: Malcolm Dunstan & Associates
Location: 40 km NNW of Constantine, Eastern Algeria
River: El Kabir
Height: 118 m
Length: 714 m
Volume of RCC: 1 690 000 m3
Volume of dam: 1 900 000 m3
Reservoir capacity: 963M m3
Design flood: 13 230 m3/sec
Start of Project: 01.01.1993 (initial contract)
Start of RCC: 18.10.1998
Completion of RCC: 07.07.2000
Completion of Project: 31.12.2000
Forming of upstream face: 1m of immersion-vibrated concrete
against vertical steel formwork
Forming of downstream face: 1m of immersion-vibrated
concrete against stepped steel formwork at a slope of 0.80:1 (H:V)
Forming of spillway: Reinforced concrete slab cast on
top of the stepped downstream face
Mixture proportions:
ASTM Type-II
cement 82 kg/m3
ASTM Class F
flyash 143 kg/m3
Water 101 kg/m3
Coarse aggregate
1335 kg/m3
Fine aggregate
750 kg/m3
Workability:
Loaded VeBe time
15 - 20 sec±

January 1999 - Split-level construction
being used in the integral coffer dam
(click on image to enlarge) |

May 1999 - Placement of RCC downstream of
the integral coffer dam
(click on image to enlarge) |

September 1999 - 'Swinger' loading 35-tonne
dump trucks with RCC
(click on image to enlarge) |

September 1999 - Large and small vibratory
rollers operating alongside formwork for middle gallery
(click on image to enlarge) |

September 1999 - Twin concrete plants each
containing 2 x 4-m3 twin-shaft batch mixers
(click on image to enlarge) |

September 1999 - Overall view of concrete
production area from cable-stayed bridge
(click on image to enlarge) |

September 1999 - Dam under construction
from upstream
(click on image to enlarge) |

February 2000 - Concrete plant and bridge
from conveyor
(click on image to enlarge) |

May 2000 - Start of construction of the
spillway on top of the stepped downstream face
(click on image to enlarge) |

Typical core extracted from the RCC in Beni
Haroun dam
(click on image to enlarge) |

May 2000 - Placement of RCC in left non-spillway
section
(click on image to enlarge) |

July 2000 - Placement of RCC in right non-spillway
section
(click on image to enlarge) |

December 2000 - Beni Haroun dam at night
nearing completion
(click on image to enlarge) |

May 2001 - Upstream face of completed Beni
Haroun dam
(click on image to enlarge) |
^ top of page ^