Upper Stillwater Dam

<:: Return to list

Greater Stillwater Dam  (click to enlarge)Owner: Central Utah Water Conservancy District
Designer: United States Bureau of Reclamation
Contractor: Tyger Construction Co. Inc. (Guy F. Atkinson Group)
Consultant to Designer: Dr M.R.H. Dunstan
Location: Duchesne, Duchesne County, Utah, USA
River: Rock Creek
Height: 91 m
Length: 815 m
Volume of RCC: 1 125 000 m3
Volume of dam: 1 281 000 m3
Reservoir capacity: 37M m3
Design flood: 2125 m3/sec
Start of Project: 01.12.1983
Start of RCC: 01.09.1985
Completion of RCC: 10.08.1987 (Two 7-month winter closedowns)
Completion of Project: 31.12.1987
Forming of upstream face: Horizontally-slipformed interlocking facing elements in a vertical face
Forming of downstream face: Horizontally-slipformed interlocking facing elements with slopes of 0.32 and 0.60:1 (H:V)
Forming of spillway: Horizontally-slipformed stepped interlocking facing elements with slopes of 0.32 and 0.60:1 (H:V)
Mixture proportions:
ASTM Type-I cement 79 kg/m3
ASTM Class F flyash 173 kg/m3
Water 98 kg/m3
Coarse aggregate 1325 kg/m3
Fine aggregate 680 kg/m3
Workability:
Loaded VeBe time 20 sec± (1987 season)

October 1985 - End of 1985 season showing RCC covered with insulation  (click to enlarge)
October 1985 - End of 1985 season showing RCC covered with insulation
(click on image to enlarge)
June 1986 - Start of 1986 season from left abutment  (click to enlarge)
June 1986 - Start of 1986 season from left abutment
(click on image to enlarge)
June 1986 - Loading 35-tonne dump trucks from conveyor  (click to enlarge)
June 1986 - Loading 35-tonne dump trucks from conveyor
(click on image to enlarge)
June 1986 - Vibratory rollers and dozer at Upper Stillwater  (click to enlarge)
June 1986 - Vibratory rollers and dozer at Upper Stillwater
(click on image to enlarge)
June 1986 - Slipforming of an upstream facing element  (click to enlarge)
June 1986 - Slipforming of an upstream facing element
(click on image to enlarge)
June 1986 - Laser-guided off-set slipform paver slipforming an upstream facing element  (click to enlarge)
June 1986 - Laser-guided off-set slipform paver slipforming an upstream facing element
(click on image to enlarge)
June 1986 - Close-up of the finish on the inside of an upstream facing element  (click to enlarge)
June 1986 - Close-up of the finish on the inside of an upstream facing element
(click on image to enlarge)
October 1986 - End of 1986 season (after a 128-day construction season)  (click to enlarge)
October 1986 - End of 1986 season (after a 128-day construction season)
(click on image to enlarge)
June 1987 - Concrete plant showing very large flyash silo  (click to enlarge)
June 1987 - Concrete plant showing very large flyash silo
(click on image to enlarge)
June 1987 - RCC being spread using spreader-box on rear of truck  (click to enlarge)
June 1987 - RCC being spread using spreader-box on rear of truck
(click on image to enlarge)
September 1987 - Construction of spillway crest block  (click to enlarge)
September 1987 - Construction of spillway crest block
(click on image to enlarge)
September 1987 - Upper Stillwater dam nearing completion  (click to enlarge)
September 1987 - Upper Stillwater dam nearing completion
(click on image to enlarge)
September 1987 - Signboard with signatures of all involved with dam  (click to enlarge)
September 1987 - Signboard with signatures of all involved with dam
(click on image to enlarge)
August 2001 - Core from Upper Stillwater 14 years after completion  (click to enlarge)
August 2001 - Core from Upper Stillwater 14 years after completion
(click on image to enlarge)
August 2001 - Close-up of 7-month joint without a bedding mix  (click to enlarge)
August 2001 - Close-up of 7-month joint without a bedding mix
(click on image to enlarge)