Dam Search Results
- Reservoir Capacity: 121 m3x106
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
| Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
| Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
| Shankou | China | Xinjiang Yili River Basin Development Authority | H | Tekes | 121 | 04/06 | - /07 | - /08 | - /09 | 50 | 496 | |||||||||||||
| Guanyin | China | Guizhou Water Conservancy Investment Group Co, Ltd | H I W | Guanyinsi | 121 | 12/21 | - /23 | - /26 | - /27 | 109 | ||||||||||||||
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: China
Owner: Xinjiang Yili River Basin Development Authority
Type: Gravity
Purpose(s): Hydropower
River: Tekes
Reservoir capacity: 121 m3x106
Construction Dates
Start of Project: 04/06
Start of RCC: 04/06
End of RCC: -/08
End of Project: -/09
Specifications
Height: 50 metres
Length: 496 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|

Details
Country: China
Owner: Guizhou Water Conservancy Investment Group Co, Ltd
Type: Gravity
Purpose(s): Hydropower / Irrigation / Water Supply
River: Guanyinsi
Reservoir capacity: 121 m3x106
Construction Dates
Start of Project: 12/21
Start of RCC: 12/21
End of RCC: -/26
End of Project: -/27
Specifications
Height: 109 metres
Length: -
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|

Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates