Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
Poço do MagroBrazilCODEVASF (Companhia de Desenvolvimento dos Vales do São Francisco e do Parnaíba)WPoço do Magro32- /03- /04- /05- /06225405868        6416(N)
LurberriaFranceAgglomeration Sud Pays BasqueFNivelle4- /06- /07- /07- /0822168 190           
Sidi el MahjoubMoroccoDirection des Aménagements HydrauliquesIfrane1- /06- /07- /08- /0922 1518V(5)1.00(1)*1.00(1)*     
Deep Creek Nº5DUSAYadkin County and NRCSF WDeep Creek1512/0804/0912/0907/10222263945V(3')0.80(3')*0.80(1)*3003008989(F)
CristalandiaBrazilEMBASA (Empresa Baiana de Aguas e Saneamento S.A)Wde Contas17- /05- /07- /0901/10223376168           
MoínhoBrazilStatkraft (Moinho S.A.)HBernado José1- /09- /10- /11- /1122126925        6817(N)
Toca do TigreBrazilCJ Hydro - Geraçao de Energia S.AHTurvo6- /09- /11- /12- /1322237             
Göle DurançamTurkeyDSI - State Hydraulic WorksIKür Çayı37- /16- /19- /23- /242210722 V 0.70        

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: Brazil

Owner: CODEVASF (Companhia de Desenvolvimento dos Vales do São Francisco e do Parnaíba)

Type: Gravity

Purpose(s): Water Supply

River: Poço do Magro

Reservoir capacity: 32 m3x106

Construction Dates

Start of Project: -/03

Start of RCC: -/03

End of RCC: -/05

End of Project: -/06

Specifications

Height: 22 metres

Length: 540 metres

Volume of RCC: 58 m3x103

Total volume: 68 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
64
Pozzolan (kg/m3)Pozzolan Type
16Natural pozzolan (ASTM Class N)
  
Poço do Magro completed
Poço do Magro completed

Full Dam Information

Details

Country: France

Owner: Agglomeration Sud Pays Basque

Type: Gravity

Purpose(s): Flood Control

River: Nivelle

Reservoir capacity: 4 m3x106

Construction Dates

Start of Project: -/06

Start of RCC: -/06

End of RCC: -/07

End of Project: -/08

Specifications

Height: 22 metres

Length: 168 metres

Volume of RCC: -

Total volume: 190 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Lurberria completed
Lurberria completed

Full Dam Information

Details

Country: Morocco

Owner: Direction des Aménagements Hydrauliques

Type: Gravity

Purpose(s): unknown

River: Ifrane

Reservoir capacity: 1 m3x106

Construction Dates

Start of Project: -/06

Start of RCC: -/06

End of RCC: -/08

End of Project: -/09

Specifications

Height: 22 metres

Length: -

Volume of RCC: 15 m3x103

Total volume: 18 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against precast concrete panels
Downstream
SlopeType
1.00Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
1.00Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Sidi el Mahjoub completed
Sidi el Mahjoub completed

Full Dam Information

Details

Country: USA

Owner: Yadkin County and NRCS

Type: Gravity

Purpose(s): Flood Control / Water Supply

River: Deep Creek

Reservoir capacity: 15 m3x106

Construction Dates

Start of Project: 12/08

Start of RCC: 12/08

End of RCC: 12/09

End of Project: 07/10

Specifications

Height: 22 metres

Length: 226 metres

Volume of RCC: 39 m3x103

Total volume: 45 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.80RCC against formwork (GEVR/GE-RCC)  [stepped face]
Spillway
SlopeType
0.80Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
89
Pozzolan (kg/m3)Pozzolan Type
89Low-lime flyash (ASTM Class F)
  
Deep Creek Nº5D completed
Deep Creek Nº5D completed

Full Dam Information

Details

Country: Brazil

Owner: EMBASA (Empresa Baiana de Aguas e Saneamento S.A)

Type: Gravity

Purpose(s): Water Supply

River: de Contas

Reservoir capacity: 17 m3x106

Construction Dates

Start of Project: -/05

Start of RCC: -/05

End of RCC: -/09

End of Project: 01/10

Specifications

Height: 22 metres

Length: 337 metres

Volume of RCC: 61 m3x103

Total volume: 68 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Cristalandia completed
Cristalandia completed

Full Dam Information

Details

Country: Brazil

Owner: Statkraft (Moinho S.A.)

Type: Gravity

Purpose(s): Hydropower

River: Bernado José

Reservoir capacity: 1 m3x106

Construction Dates

Start of Project: -/09

Start of RCC: -/09

End of RCC: -/11

End of Project: -/11

Specifications

Height: 22 metres

Length: 126 metres

Volume of RCC: 9 m3x103

Total volume: 25 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
68
Pozzolan (kg/m3)Pozzolan Type
17Natural pozzolan (ASTM Class N)
  
Moínho completed
Moínho completed

Full Dam Information

Details

Country: Brazil

Owner: CJ Hydro - Geraçao de Energia S.A

Type: Gravity

Purpose(s): Hydropower

River: Turvo

Reservoir capacity: 6 m3x106

Construction Dates

Start of Project: -/09

Start of RCC: -/09

End of RCC: -/12

End of Project: -/13

Specifications

Height: 22 metres

Length: 237 metres

Volume of RCC: -

Total volume: -

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Toca do Tigre completed
Toca do Tigre completed

Full Dam Information

Details

Country: Turkey

Owner: DSI - State Hydraulic Works

Type: Gravity

Purpose(s): Irrigation

River: Kür Çayı

Reservoir capacity: 37 m3x106

Construction Dates

Start of Project: -/16

Start of RCC: -/16

End of RCC: -/23

End of Project: -/24

Specifications

Height: 22 metres

Length: 107 metres

Volume of RCC: 22 m3x103

Total volume: -

Construction Methods

Facings

Upstream
SlopeType
Vertical 
Downstream
SlopeType
0.70 
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Photo coming soon

 

Search again