Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
GaotangpingChinaHydropower Bureau, Lanshan CountyHYonghe9- /84- /86- /88- /9052180 220          (F)
AsariJapanHokkaido PrefectureF WAsari907/8610/8709/9003/9374390259517V
0.30
(1)
(1)
0.80(1)0.80(1)1805009624(F)
Xibingxi
[A-G]
ChinaDepartment of Electric Power, Lonyan City, Fujian ProvinceH WLongshanxi908/9312/9407/9510/9564932533V
0.08
(4)
(4)
0.65(3)ogee
0.65
(13)300 -
350
300 -
350
80
79
120
105
(F)
ShimagawaJapanGunma PrefectureF WShima903/91- /9405/9603/9890330390516V
0.50
(1)
(1)
0.80(1)0.80(1)2507508436(F)
SuçatiTurkeyERE Electricity Co.HGüredin Creek901/9802/9910/9910/99361925560V(7)0.80(7)0.80(12)30030050100(S)
WalaJordanJordan Valley Authority, Ministry of Water and IrrigationGWala901/9910/0004/0204/03523002402600.30(1)0.70(1)*0.70(1)*300300120
100
0
0
(-) -
Engenheiro Henrique KotzianBrazilBME EnergiaHIvaí9- /06- /07- /0804/09402265876           

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: China

Owner: Hydropower Bureau, Lanshan County

Type: Gravity

Purpose(s): Hydropower

River: Yonghe

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: -/84

Start of RCC: -/84

End of RCC: -/88

End of Project: -/90

Specifications

Height: 52 metres

Length: 180 metres

Volume of RCC: -

Total volume: 220 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
 Low-lime flyash (ASTM Class F)
  
Photo coming soon

Full Dam Information

Details

Country: Japan

Owner: Hokkaido Prefecture

Type: Gravity

Purpose(s): Flood Control / Water Supply

River: Asari

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 07/86

Start of RCC: 07/86

End of RCC: 09/90

End of Project: 03/93

Specifications

Height: 74 metres

Length: 390 metres

Volume of RCC: 259 m3x103

Total volume: 517 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
0.30Traditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork
Spillway
SlopeType
0.80Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
180500

Cementitious material

Cement (kg/m3)
96
Pozzolan (kg/m3)Pozzolan Type
24Low-lime flyash (ASTM Class F)
  
Asari completed
Asari completed

Full Dam Information

Details

Country: China

Owner: Department of Electric Power, Lonyan City, Fujian Province

Type: Arch-Gravity

Purpose(s): Hydropower / Water Supply

River: Longshanxi

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 08/93

Start of RCC: 08/93

End of RCC: 07/95

End of Project: 10/95

Specifications

Height: 64 metres

Length: 93 metres

Volume of RCC: 25 m3x103

Total volume: 33 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork with external geomembrane
0.08RCC against formwork with external geomembrane
Downstream
SlopeType
0.65RCC against formwork
Spillway
SlopeType
ogeeReinforced concrete cast against precast units or slip-formed facing elements
0.65 

Placement

Layers (mm)Lifts (mm)
300  -300  -
350350

Cementitious material

Cement (kg/m3)
80
79
Pozzolan (kg/m3)Pozzolan Type
120Low-lime flyash (ASTM Class F)
105 
Xibingxi completed
Xibingxi completed

Full Dam Information

Details

Country: Japan

Owner: Gunma Prefecture

Type: Gravity

Purpose(s): Flood Control / Water Supply

River: Shima

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 03/91

Start of RCC: 03/91

End of RCC: 05/96

End of Project: 03/98

Specifications

Height: 90 metres

Length: 330 metres

Volume of RCC: 390 m3x103

Total volume: 516 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
0.50Traditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork
Spillway
SlopeType
0.80Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
250750

Cementitious material

Cement (kg/m3)
84
Pozzolan (kg/m3)Pozzolan Type
36Low-lime flyash (ASTM Class F)
  
Shimagawa completed
Shimagawa completed

Full Dam Information

Details

Country: Turkey

Owner: ERE Electricity Co.

Type: Gravity

Purpose(s): Hydropower

River: Güredin Creek

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 01/98

Start of RCC: 01/98

End of RCC: 10/99

End of Project: 10/99

Specifications

Height: 36 metres

Length: 192 metres

Volume of RCC: 55 m3x103

Total volume: 60 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against precast concrete panels
Downstream
SlopeType
0.80RCC against precast concrete panels
Spillway
SlopeType
0.80Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
50
Pozzolan (kg/m3)Pozzolan Type
100Ground-granulated blast-furnace slag
  
Suçati completed
Suçati completed

Full Dam Information

Details

Country: Jordan

Owner: Jordan Valley Authority, Ministry of Water and Irrigation

Type: Gravity

Purpose(s): Groundwater Recharge

River: Wala

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 01/99

Start of RCC: 01/99

End of RCC: 04/02

End of Project: 04/03

Specifications

Height: 52 metres

Length: 300 metres

Volume of RCC: 240 m3x103

Total volume: 260 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.30Traditional concrete against formwork
Downstream
SlopeType
0.70Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
0.70Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
120
100
Pozzolan (kg/m3)Pozzolan Type
0No pozzolan used  -
0 
Wala completed
Wala completed

Full Dam Information

Details

Country: Brazil

Owner: BME Energia

Type: Gravity

Purpose(s): Hydropower

River: Ivaí

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: -/06

Start of RCC: -/06

End of RCC: -/08

End of Project: 04/09

Specifications

Height: 40 metres

Length: 226 metres

Volume of RCC: 58 m3x103

Total volume: 76 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Engenheiro Henrique Kotzian completed
Engenheiro Henrique Kotzian completed

 

Search again