Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
Tongjiezi (with Niurixigou saddle dam)ChinaDepartment of Hydroelectric Power, Sichuan ProvinceF H I NDaduhe 20001/8510/8812/8910/9488284407855V(1)0.75(10)0.75(1)300 -
500
300 -
500
79
82
79
83
(F)
Fenhe Nº2ChinaDepartment of Water Resources, Shanxi ProvinceF H WFenhe13311/9608/9803/9906/0088350362448V
0.20
(1)
(1)
0.75(5)0.75(1)3003000127
60
84
93
(F)
Shaba
[A]
ChinaGuizhou Zhongsui Energy Ltd.HHongduhe99- /03- /04- /04- /05881486790           
ZaoshiChinaLishui Basin Hydraulic and Hydroelectric Development CorporationF H N WDieshui1439- /04- /05- /06- /0788351450930V
0.25
(3')0.80(3')0.75(1)300300053
83
99
102
(F)
Kavsak BendiTurkeyEnerjisa En.Ür. A.S.HSeyhan - /09- /10- /12- /1388   0.20(1)0.80(1)       
Pembelik
[H-F]
TurkeyDarenhes A.S.HPeriSuyu35811/1003/1310/1412/14885007608380.20(3')0.80(3')0.80(12)30012001200(-) -
Trung SonVietnamEVN (Electrictie de Vietnam)F HMa34911/1204/1408/1602/17884987701140V
0.35
(3')
(3')*
0.65(3')*0.65(12)30030060
70
140
150
(N)
YesilkavakTurkeyDSI - State Hydraulic WorksIKisik30- /14- /16- /18- /1988452727809V(3)1.00(3)1.00(12)300    

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: China

Owner: Department of Hydroelectric Power, Sichuan Province

Type: Gravity

Purpose(s): Flood Control / Hydropower / Irrigation / Navigation

River: Daduhe

Reservoir capacity: 200 m3x106

Construction Dates

Start of Project: 01/85

Start of RCC: 01/85

End of RCC: 12/89

End of Project: 10/94

Specifications

Height: 88 metres

Length: 284 metres

Volume of RCC: 407 m3x103

Total volume: 855 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
Downstream
SlopeType
0.75RCC against precast concrete blocks
Spillway
SlopeType
0.75Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
300  -300  -
500500

Cementitious material

Cement (kg/m3)
79
82
Pozzolan (kg/m3)Pozzolan Type
79Low-lime flyash (ASTM Class F)
83 
Photo coming soon

Full Dam Information

Details

Country: China

Owner: Department of Water Resources, Shanxi Province

Type: Gravity

Purpose(s): Flood Control / Hydropower / Water Supply

River: Fenhe

Reservoir capacity: 133 m3x106

Construction Dates

Start of Project: 11/96

Start of RCC: 11/96

End of RCC: 03/99

End of Project: 06/00

Specifications

Height: 88 metres

Length: 350 metres

Volume of RCC: 362 m3x103

Total volume: 448 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
0.20Traditional concrete against formwork
Downstream
SlopeType
0.75Traditional concrete against precast concrete panels
Spillway
SlopeType
0.75Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
3003000

Cementitious material

Cement (kg/m3)
127
60
Pozzolan (kg/m3)Pozzolan Type
84Low-lime flyash (ASTM Class F)
93 
Fenhe Nº2 completed
Fenhe Nº2 completed

Full Dam Information

Details

Country: China

Owner: Guizhou Zhongsui Energy Ltd.

Type: Thin Arch

Purpose(s): Hydropower

River: Hongduhe

Reservoir capacity: 99 m3x106

Construction Dates

Start of Project: -/03

Start of RCC: -/03

End of RCC: -/04

End of Project: -/05

Specifications

Height: 88 metres

Length: 148 metres

Volume of RCC: 67 m3x103

Total volume: 90 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Shaba completed
Shaba completed

Full Dam Information

Details

Country: China

Owner: Lishui Basin Hydraulic and Hydroelectric Development Corporation

Type: Gravity

Purpose(s): Flood Control / Hydropower / Navigation / Water Supply

River: Dieshui

Reservoir capacity: 1439 m3x106

Construction Dates

Start of Project: -/04

Start of RCC: -/04

End of RCC: -/06

End of Project: -/07

Specifications

Height: 88 metres

Length: 351 metres

Volume of RCC: 450 m3x103

Total volume: 930 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
0.25 
Downstream
SlopeType
0.80RCC against formwork (GEVR/GE-RCC)
Spillway
SlopeType
0.75Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
3003000

Cementitious material

Cement (kg/m3)
53
83
Pozzolan (kg/m3)Pozzolan Type
99Low-lime flyash (ASTM Class F)
102 
Zaoshi completed
Zaoshi completed

Full Dam Information

Details

Country: Turkey

Owner: Enerjisa En.Ür. A.S.

Type: Gravity

Purpose(s): Hydropower

River: Seyhan

Reservoir capacity: -

Construction Dates

Start of Project: -/09

Start of RCC: -/09

End of RCC: -/12

End of Project: -/13

Specifications

Height: 88 metres

Length: -

Volume of RCC: -

Total volume: -

Construction Methods

Facings

Upstream
SlopeType
0.20Traditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Photo coming soon

Full Dam Information

Details

Country: Turkey

Owner: Darenhes A.S.

Type: Hardfill

Purpose(s): Hydropower

River: PeriSuyu

Reservoir capacity: 358 m3x106

Construction Dates

Start of Project: 11/10

Start of RCC: 11/10

End of RCC: 10/14

End of Project: 12/14

Specifications

Height: 88 metres

Length: 500 metres

Volume of RCC: 760 m3x103

Total volume: 838 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.20RCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.80RCC against formwork (GEVR/GE-RCC)
Spillway
SlopeType
0.80Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
3001200

Cementitious material

Cement (kg/m3)
120
Pozzolan (kg/m3)Pozzolan Type
0No pozzolan used  -
  
Pembelik completed
Pembelik completed

Full Dam Information

Details

Country: Vietnam

Owner: EVN (Electrictie de Vietnam)

Type: Gravity

Purpose(s): Flood Control / Hydropower

River: Ma

Reservoir capacity: 349 m3x106

Construction Dates

Start of Project: 11/12

Start of RCC: 11/12

End of RCC: 08/16

End of Project: 02/17

Specifications

Height: 88 metres

Length: 498 metres

Volume of RCC: 770 m3x103

Total volume: 1140 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
0.35RCC against formwork (GEVR/GE-RCC)  [stepped face]
Downstream
SlopeType
0.65RCC against formwork (GEVR/GE-RCC)  [stepped face]
Spillway
SlopeType
0.65Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
60
70
Pozzolan (kg/m3)Pozzolan Type
140Natural pozzolan (ASTM Class N)
150 
Trung Son under construction
Trung Son under construction

Full Dam Information

Details

Country: Turkey

Owner: DSI - State Hydraulic Works

Type: Gravity

Purpose(s): Irrigation

River: Kisik

Reservoir capacity: 30 m3x106

Construction Dates

Start of Project: -/14

Start of RCC: -/14

End of RCC: -/18

End of Project: -/19

Specifications

Height: 88 metres

Length: 452 metres

Volume of RCC: 727 m3x103

Total volume: 809 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork
Downstream
SlopeType
1.00RCC against formwork
Spillway
SlopeType
1.00Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300 

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Photo coming soon

 