Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
Santa EugeniaSpainSociedad Española de Carburos Metálicos S.A.HXallas1701/8706/8706/8810/88842902252540.05(3)0.75
0.35
(3)*
(3)*
0.75(1)25025088
72
152
145
(F)
Asahi OgawaJapanToyama PrefectureF HOgawa503/8305/8606/8806/9084260268361V
0.90
(1)
(1)
0.80(1)0.80(1)1805009624(F)
ShibanshuiChinaFengdu Water Resources BureauH RLongxihe10512/9204/9412/9712/9884445335564V(3')0.65(1)0.65(13)3001000126
60
84
90
(F)
LeidatanChinaLeidatan CorporationHYingtaoyuangou9403/03- /05- /0606/0784202240340V(3')0.70(3')0.70(1)     
HantangangSouth KoreaKwater (Korean Water Resources CorporationF I WHantan27002/0907/1007/1412/1484690 709V(1) (1) (1)2507509139(F)
TiouineMoroccoDirection des Aménagements HydrauliquesF I WIriri27005/10- /11- /14- /1584202 380V(1)0.80(1)*0.80(1)*  1000(-) -

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: Spain

Owner: Sociedad Española de Carburos Metálicos S.A.

Type: Gravity

Purpose(s): Hydropower

River: Xallas

Reservoir capacity: 17 m3x106

Construction Dates

Start of Project: 01/87

Start of RCC: 01/87

End of RCC: 06/88

End of Project: 10/88

Specifications

Height: 84 metres

Length: 290 metres

Volume of RCC: 225 m3x103

Total volume: 254 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.05RCC against formwork
Downstream
SlopeType
0.75RCC against formwork  [stepped face]
0.35RCC against formwork  [stepped face]
Spillway
SlopeType
0.75Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
250250

Cementitious material

Cement (kg/m3)
88
72
Pozzolan (kg/m3)Pozzolan Type
152Low-lime flyash (ASTM Class F)
145 
Santa Eugenia completed
Santa Eugenia completed

Full Dam Information

Details

Country: Japan

Owner: Toyama Prefecture

Type: Gravity

Purpose(s): Flood Control / Hydropower

River: Ogawa

Reservoir capacity: 5 m3x106

Construction Dates

Start of Project: 03/83

Start of RCC: 03/83

End of RCC: 06/88

End of Project: 06/90

Specifications

Height: 84 metres

Length: 260 metres

Volume of RCC: 268 m3x103

Total volume: 361 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
0.90Traditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork
Spillway
SlopeType
0.80Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
180500

Cementitious material

Cement (kg/m3)
96
Pozzolan (kg/m3)Pozzolan Type
24Low-lime flyash (ASTM Class F)
  
Asahi Ogawa completed
Asahi Ogawa completed

Full Dam Information

Details

Country: China

Owner: Fengdu Water Resources Bureau

Type: Gravity

Purpose(s): Hydropower / Recreation

River: Longxihe

Reservoir capacity: 105 m3x106

Construction Dates

Start of Project: 12/92

Start of RCC: 12/92

End of RCC: 12/97

End of Project: 12/98

Specifications

Height: 84 metres

Length: 445 metres

Volume of RCC: 335 m3x103

Total volume: 564 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.65Traditional concrete against formwork
Spillway
SlopeType
0.65Reinforced concrete cast against precast units or slip-formed facing elements

Placement

Layers (mm)Lifts (mm)
3001000

Cementitious material

Cement (kg/m3)
126
60
Pozzolan (kg/m3)Pozzolan Type
84Low-lime flyash (ASTM Class F)
90 
Shibanshui completed
Shibanshui completed

Full Dam Information

Details

Country: China

Owner: Leidatan Corporation

Type: Gravity

Purpose(s): Hydropower

River: Yingtaoyuangou

Reservoir capacity: 94 m3x106

Construction Dates

Start of Project: 03/03

Start of RCC: 03/03

End of RCC: -/06

End of Project: 06/07

Specifications

Height: 84 metres

Length: 202 metres

Volume of RCC: 240 m3x103

Total volume: 340 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.70RCC against formwork (GEVR/GE-RCC)
Spillway
SlopeType
0.70Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Leidatan under construction
Leidatan under construction

Full Dam Information

Details

Country: South Korea

Owner: Kwater (Korean Water Resources Corporation

Type: Gravity

Purpose(s): Flood Control / Irrigation / Water Supply

River: Hantan

Reservoir capacity: 270 m3x106

Construction Dates

Start of Project: 02/09

Start of RCC: 02/09

End of RCC: 07/14

End of Project: 12/14

Specifications

Height: 84 metres

Length: 690 metres

Volume of RCC: -

Total volume: 709 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
Downstream
SlopeType
 Traditional concrete against formwork
Spillway
SlopeType
 Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
250750

Cementitious material

Cement (kg/m3)
91
Pozzolan (kg/m3)Pozzolan Type
39Low-lime flyash (ASTM Class F)
  
Hantangang completed
Hantangang completed

Full Dam Information

Details

Country: Morocco

Owner: Direction des Aménagements Hydrauliques

Type: Gravity

Purpose(s): Flood Control / Irrigation / Water Supply

River: Iriri

Reservoir capacity: 270 m3x106

Construction Dates

Start of Project: 05/10

Start of RCC: 05/10

End of RCC: -/14

End of Project: -/15

Specifications

Height: 84 metres

Length: 202 metres

Volume of RCC: -

Total volume: 380 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
0.80Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
100
Pozzolan (kg/m3)Pozzolan Type
0No pozzolan used  -
  
Tiouine on Google Earth
Tiouine on Google Earth

 

Search again

Please note: only dams with known co-ordinates will appear on this map.

Your search returned no dams with known co-ordinates