SEARCHING
... please wait

Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
ShimantanChinaDepartment of Water Resources, Henan ProvinceF I WGunhe 12007/9304/9412/9507/9641650272351V(3')0.75(3)*0.75(1)30030098
51
98
107
(F)
AntacotoPeruMantaro120- /98- /98- /99- /991765            (-)
ChalilloBelizeBelize Electric Co. Ltd (BECOL) and A. Fortis Co., CanadaHMacal12007/0303/0410/0512/06684251802100.20(1)0.75(3')*0.75(12)30036001050(N)
BoussiabaAlgeriaANBT (Agence Nationale des Barrages et Transferts)WBoussiaba12012/0605/0811/0808/0951310160190V(2) (1)* (1)30030011228(F)
Upper Wawa
[H-F]
PhilippinesWawa JV Co. Inc. (Prime Infrastructure Capital Inc and San Lorenzo Ruiz Builders and Developers Group)WMarikina12006/2101/23- /24- /2587439103510430.60(3')0.80(3')*0.80(3')*300360080
70
120
110
(F)

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: China

Owner: Department of Water Resources, Henan Province

Type: Gravity

Purpose(s): Flood Control / Irrigation / Water Supply

River: Gunhe

Reservoir capacity: 120 m3x106

Construction Dates

Start of Project: 07/93

Start of RCC: 07/93

End of RCC: 12/95

End of Project: 07/96

Specifications

Height: 41 metres

Length: 650 metres

Volume of RCC: 272 m3x103

Total volume: 351 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.75RCC against formwork  [stepped face]
Spillway
SlopeType
0.75Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
98
51
Pozzolan (kg/m3)Pozzolan Type
98Low-lime flyash (ASTM Class F)
107 
Shimantan on Google Earth
Shimantan on Google Earth

Full Dam Information

Details

Country: Peru

Owner: -

Type: Gravity

Purpose(s): unknown

River: Mantaro

Reservoir capacity: 120 m3x106

Construction Dates

Start of Project: -/98

Start of RCC: -/98

End of RCC: -/99

End of Project: -/99

Specifications

Height: 17 metres

Length: 65 metres

Volume of RCC: -

Total volume: -

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
 No pozzolan used
  
Antacoto completed
Antacoto completed

Full Dam Information

Details

Country: Belize

Owner: Belize Electric Co. Ltd (BECOL) and A. Fortis Co., Canada

Type: Gravity

Purpose(s): Hydropower

River: Macal

Reservoir capacity: 120 m3x106

Construction Dates

Start of Project: 07/03

Start of RCC: 07/03

End of RCC: 10/05

End of Project: 12/06

Specifications

Height: 68 metres

Length: 425 metres

Volume of RCC: 180 m3x103

Total volume: 210 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.20Traditional concrete against formwork
Downstream
SlopeType
0.75RCC against formwork (GEVR/GE-RCC)  [stepped face]
Spillway
SlopeType
0.75Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
3003600

Cementitious material

Cement (kg/m3)
105
Pozzolan (kg/m3)Pozzolan Type
0Natural pozzolan (ASTM Class N)
  
Chalillo completed
Chalillo completed

Full Dam Information

Details

Country: Algeria

Owner: ANBT (Agence Nationale des Barrages et Transferts)

Type: Gravity

Purpose(s): Water Supply

River: Boussiaba

Reservoir capacity: 120 m3x106

Construction Dates

Start of Project: 12/06

Start of RCC: 12/06

End of RCC: 11/08

End of Project: 08/09

Specifications

Height: 51 metres

Length: 310 metres

Volume of RCC: 160 m3x103

Total volume: 190 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork with external geomembrane
Downstream
SlopeType
 Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
 Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
112
Pozzolan (kg/m3)Pozzolan Type
28Low-lime flyash (ASTM Class F)
  
Boussiaba on Google Earth
Boussiaba on Google Earth

Full Dam Information

Details

Country: Philippines

Owner: Wawa JV Co. Inc. (Prime Infrastructure Capital Inc and San Lorenzo Ruiz Builders and Developers Group)

Type: Hardfill

Purpose(s): Water Supply

River: Marikina

Reservoir capacity: 120 m3x106

Construction Dates

Start of Project: 06/21

Start of RCC: 06/21

End of RCC: -/24

End of Project: -/25

Specifications

Height: 87 metres

Length: 439 metres

Volume of RCC: 1035 m3x103

Total volume: 1043 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.60RCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.80RCC against formwork (GEVR/GE-RCC)  [stepped face]
Spillway
SlopeType
0.80RCC against formwork (GEVR/GE-RCC)  [stepped face]

Placement

Layers (mm)Lifts (mm)
3003600

Cementitious material

Cement (kg/m3)
80
70
Pozzolan (kg/m3)Pozzolan Type
120Low-lime flyash (ASTM Class F)
110 
Photo coming soon

 

Search again

Please note: only dams with known co-ordinates will appear on this map.

Your search returned no dams with known co-ordinates