Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
SuçatiTurkeyERE Electricity Co.HGüredin Creek901/9802/9910/9910/99361925560V(7)0.80(7)0.80(12)30030050100(S)
Pedras AltasBrazilCERB (Companhia de Engenharia Rural da Bahia)F I R WItapicuru - /00- /00- /01- /01242204260      3003003441(-) -
AmataMexicoCFE (Comisión Federal de Electricidad)ISan Lorenzo1411/0311/0404/0506/05302184260V
1.00
(8)1.00(3)*1.00(12)3003001200(-) -
RkizaMoroccoF I W 17- /13- /15- /16- /17265005560V(5)0.85(1)*0.85(1)*     
BouhdidAlgeriaDirection de l’Hydralique de la Wilaya de AnnabaFOued Bouhdid1- /18- /19- /20- /2130260 600.10 0.90        

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: Turkey

Owner: ERE Electricity Co.

Type: Gravity

Purpose(s): Hydropower

River: Güredin Creek

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 01/98

Start of RCC: 01/98

End of RCC: 10/99

End of Project: 10/99

Specifications

Height: 36 metres

Length: 192 metres

Volume of RCC: 55 m3x103

Total volume: 60 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against precast concrete panels
Downstream
SlopeType
0.80RCC against precast concrete panels
Spillway
SlopeType
0.80Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
50
Pozzolan (kg/m3)Pozzolan Type
100Ground-granulated blast-furnace slag
  
Suçati completed
Suçati completed

Full Dam Information

Details

Country: Brazil

Owner: CERB (Companhia de Engenharia Rural da Bahia)

Type: Gravity

Purpose(s): Flood Control / Irrigation / Recreation / Water Supply

River: Itapicuru

Reservoir capacity: -

Construction Dates

Start of Project: -/00

Start of RCC: -/00

End of RCC: -/01

End of Project: -/01

Specifications

Height: 24 metres

Length: 220 metres

Volume of RCC: 42 m3x103

Total volume: 60 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
34
Pozzolan (kg/m3)Pozzolan Type
41No pozzolan used  -
  
Pedras Altas completed
Pedras Altas completed

Full Dam Information

Details

Country: Mexico

Owner: CFE (Comisión Federal de Electricidad)

Type: Gravity

Purpose(s): Irrigation

River: San Lorenzo

Reservoir capacity: 14 m3x106

Construction Dates

Start of Project: 11/03

Start of RCC: 11/03

End of RCC: 04/05

End of Project: 06/05

Specifications

Height: 30 metres

Length: 218 metres

Volume of RCC: 42 m3x103

Total volume: 60 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against precast concrete panels with geomembrane
1.00 
Downstream
SlopeType
1.00RCC against formwork  [stepped face]
Spillway
SlopeType
1.00Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
120
Pozzolan (kg/m3)Pozzolan Type
0No pozzolan used  -
  
Amata completed
Amata completed

Full Dam Information

Details

Country: Morocco

Owner: -

Type: Gravity

Purpose(s): Flood Control / Irrigation / Water Supply

River: -

Reservoir capacity: 17 m3x106

Construction Dates

Start of Project: -/13

Start of RCC: -/13

End of RCC: -/16

End of Project: -/17

Specifications

Height: 26 metres

Length: 500 metres

Volume of RCC: 55 m3x103

Total volume: 60 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against precast concrete panels
Downstream
SlopeType
0.85Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
0.85Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Rkiza under construction
Rkiza under construction

Full Dam Information

Details

Country: Algeria

Owner: Direction de l’Hydralique de la Wilaya de Annaba

Type: Gravity

Purpose(s): Flood Control

River: Oued Bouhdid

Reservoir capacity: 1 m3x106

Construction Dates

Start of Project: -/18

Start of RCC: -/18

End of RCC: -/20

End of Project: -/21

Specifications

Height: 30 metres

Length: 260 metres

Volume of RCC: -

Total volume: 60 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.10 
Downstream
SlopeType
0.90 
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Photo coming soon

 

Search again