Priest Rapids Right Embankment

Download PDF data sheet
Photo coming soon

Particulars

Owner: Grant County Public Utility District

Designer: Stantec

Contractor: IMCO Construction

Statistics

Type: Gravity

Purpose(s): Hydropower

Reservoir capacity: unknown

Height: 17 metres

Length: 564 metres

Volume of RCC: 386 m3x103

Total volume: unknown

Construction Dates

Start of Project: 10/21 (October 2021)

Start of RCC: 04/22 (April 2022)

End of RCC: 03/23 (March 2023)

End of Project: 10/23 (October 2023)

Country: USA

River: Columbia

DMS Co-ordinates: 46˚38'25.08"N, 119˚55'20.40"W

DD Co-ordinates: 46.640301, -119.922333

Facings

Upstream

SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)

Downstream

SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
0.75Unformed face of RCC

Spillway

SlopeType
none 

Placement

Layers (mm)Lifts (mm)
300300  -

Cementitious material

Cement (kg/m3)
87
Pozzolan (kg/m3)Pozzolan Type
137Low-lime flyash (ASTM Class F)