São Sebastião do Alto
Download PDF data sheet
São Sebastião do Alto completed

Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 44 m3x106
Height: 41 metres
Length: 210 metres
Volume of RCC: 51 m3x103
Total volume: 75 m3x103
Construction Dates
Start of Project: —/08 (— 2008)
Start of RCC: —/09 (— 2009)
End of RCC: —/10 (— 2010)
End of Project: —/11 (— 2011)
Country: Brazil
River: Grande
DMS Co-ordinates: 21˚56'14.01"S, 42˚5'23.94"W
DD Co-ordinates: -21.937225, -42.089985
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|