Olivenhain Dam
<:: Return to list
Owner:
San Diego County Water Authority
Designer: Parsons-Harza JV.
Contractor: Kiewit Pacific Co. Ltd.
Project Manager: Washington Infrastructure Services Inc.
Consultant to Designer: Gannett-Fleming
Consultant to Contractor: Malcolm Dunstan & Associates
Location: Escondido, California, USA
River: Escondido Creek
Height: 94 m
Length: 778 m
Volume of RCC: 1 140 000 m3
Volume of dam: 1 070 000 m3
Reservoir capacity: 30M m3
Design flood: - (reservoir filled by pumping)
Start of Project: 13.06.2001
Start of RCC: 04.02.2002
Completion of RCC: 31.10.2002
Completion of Project: 16.04.2003
Forming of upstream face: GEVR against vertical timber
formwork with external CARPI membrane
Forming of downstream face: RCC against 600-mm high stepped
steel formwork at a slope of 0.80:1 (H:V)
Forming of spillway: Immersion-vibrated concrete against
600-mm high stepped steel formwork at a slope of 0.80:1 (H:V)
Mixture proportions:
ASTM Type-II
cement 74 kg/m3
ASTM Class F
flyash 121 kg/m3
Water 119 kg/m3
Coarse aggregate
1390 kg/m3
Fine aggregate
740 kg/m3
Workability:
Loaded VeBe time
12 to 20 sec

Reservoir area before the start of the RCC
dam contract
(click on image to enlarge) |

Excavation for dam from right abutment
(click on image to enlarge) |

Satellite photograph of dam under construction
(click on image to enlarge) |

Stockpiles and concrete plant
(click on image to enlarge) |

December 2001 - Full-scale trial in right
abutment shaping block
(click on image to enlarge) |

March 2002 - Placement of RCC in left abutment
shaping block
(click on image to enlarge) |

March 2002 - Swinger loading RCC into trucks
(click on image to enlarge) |

March 2002 - Spreading grout against an
abutment
(click on image to enlarge) |

March 2002 - Vibrating GEVR against an abutment
(click on image to enlarge) |

March 2002 - GEVR after vibration but before
RCC roller compacted
(click on image to enlarge) |

April 2002 - Placement of first RCC in main
dam body
(click on image to enlarge) |

August 2002 - Olivenhain dam from downstream
(click on image to enlarge) |

July 2002 - Upstream face (formed of GEVR
against timber formwork) and Intake Tower under construction
(click on image to enlarge) |

August 2002 - Spillway training walls under
construction on the downstream face (formed of RCC compacted directly
against stepped formwork). The spillway was formed of immersion-vibrated
concrete placed at the same time as the RCC
(click on image to enlarge) |

October 2002 - Concrete plant and conveyor
from dam
(click on image to enlarge) |

October 2002 - Quarry and dam nearing completion
(click on image to enlarge) |

October 2002 - Olivenhain dam nearing completion
from left abutment
(click on image to enlarge) |

31 October 2002 - Completion of RCC placement
(1.07M m3 of RCC placed in 8.5 months)
(click on image to enlarge) |

November 2002 - Completed Olivenhain dam
from upstream
(click on image to enlarge) |

November 2002 - Completed Olivenhain dam
from downstream
(click on image to enlarge) |

3 September 2003 – Downstream face of completed dam
(click on image to enlarge) |

7 August 2003 – First water into reservoir
(click on image to enlarge) |

4 September 2003 – Dedication Ceremony
(click on image to enlarge) |
^ top of page ^