Dam Search Results
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
| Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
| Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
| Mangla Emergency Spillway Control Weir | Pakistan | WAPDA (Water and Power Development Authority) | H I | Jhelum | 6500 | 08/04 | 12/07 | 11/08 | 01/09 | 17 | 370 | 54 | 79 | V 0.30 | (3') (3')* | V 0.70 | (3') (3')* | 0.70 | (3')* | 300 | 300 | 60 | 120 | (S) |
| Khan Khwar | Pakistan | WAPDA (Water and Power Development Authority) and CTGC (China Three Gorges Corp.) | H | Duber Khwar | 04/03 | - /06 | - /10 | 04/12 | 46 | 112 | ||||||||||||||
| Gomal Zam [A-G] | Pakistan | WAPDA (Water and Power Development Authority) | F H I | Gomal | 1424 | 07/02 | 08/07 | 09/11 | 06/13 | 133 | 231 | 390 | 474 | V | 0.60 | 0.60 | 300 | 3000 to 4000 | 91 | 91 | (F) | |||
| Duber Khwar | Pakistan | WAPDA (Water and Power Development Authority) and CTGC (China Three Gorges Corp.) | H | Duber Khwar | 06/03 | - /08 | - /12 | 01/14 | 41 | 202 | ||||||||||||||
| Allai Khwar | Pakistan | WAPDA (Water and Power Development Authority) and CTGC (China Three Gorges Corp.) | H | Allai Khwar | 01/05 | - /09 | - /12 | 03/13 | 51 | 88 | ||||||||||||||
| Neelum-Jhelum | Pakistan | Neelum Jhelum Hydropower Company | H | Neelum | 8 | - /08 | - /14 | 08/16 | 11/17 | 47 | 125 | 156 | 154 | 51 | (S) | |||||||||
| Gulpur | Pakistan | WAPDA (Water and Power Development Authority) and MIRA Power Ltd. (a subsidiary of KOSEP) | H | Poonch | 22 | 09/14 | - /16 | - /18 | 02/20 | 35 | 238 | |||||||||||||
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: Pakistan
Owner: WAPDA (Water and Power Development Authority)
Type: Gravity
Purpose(s): Hydropower / Irrigation
River: Jhelum
Reservoir capacity: 6500 m3x106
Construction Dates
Start of Project: 08/04
Start of RCC: 08/04
End of RCC: 11/08
End of Project: 01/09
Specifications
Height: 17 metres
Length: 370 metres
Volume of RCC: 54 m3x103
Total volume: 79 m3x103
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
| Vertical | RCC against formwork (GEVR/GE-RCC) |
| 0.30 | RCC against formwork (GEVR/GE-RCC) [stepped face] |
Downstream
| Slope | Type |
|---|---|
| Vertical | RCC against formwork (GEVR/GE-RCC) |
| 0.70 | RCC against formwork (GEVR/GE-RCC) [stepped face] |
Spillway
| Slope | Type |
|---|---|
| 0.70 | RCC against formwork (GEVR/GE-RCC) [stepped face] |
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
| 300 | 300 |
Cementitious material
| Cement (kg/m3) |
|---|
| 60 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 120 | Ground-granulated blast-furnace slag |

Details
Country: Pakistan
Owner: WAPDA (Water and Power Development Authority) and CTGC (China Three Gorges Corp.)
Type: Gravity
Purpose(s): Hydropower
River: Duber Khwar
Reservoir capacity: -
Construction Dates
Start of Project: 04/03
Start of RCC: 04/03
End of RCC: -/10
End of Project: 04/12
Specifications
Height: 46 metres
Length: 112 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|

Details
Country: Pakistan
Owner: WAPDA (Water and Power Development Authority)
Type: Arch-Gravity
Purpose(s): Flood Control / Hydropower / Irrigation
River: Gomal
Reservoir capacity: 1424 m3x106
Construction Dates
Start of Project: 07/02
Start of RCC: 07/02
End of RCC: 09/11
End of Project: 06/13
Specifications
Height: 133 metres
Length: 231 metres
Volume of RCC: 390 m3x103
Total volume: 474 m3x103
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
| Vertical |
Downstream
| Slope | Type |
|---|---|
| 0.60 |
Spillway
| Slope | Type |
|---|---|
| 0.60 |
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
| 300 | 3000 to |
| 4000 |
Cementitious material
| Cement (kg/m3) |
|---|
| 91 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 91 | Low-lime flyash (ASTM Class F) |

Details
Country: Pakistan
Owner: WAPDA (Water and Power Development Authority) and CTGC (China Three Gorges Corp.)
Type: Gravity
Purpose(s): Hydropower
River: Duber Khwar
Reservoir capacity: -
Construction Dates
Start of Project: 06/03
Start of RCC: 06/03
End of RCC: -/12
End of Project: 01/14
Specifications
Height: 41 metres
Length: 202 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|

Details
Country: Pakistan
Owner: WAPDA (Water and Power Development Authority) and CTGC (China Three Gorges Corp.)
Type: Gravity
Purpose(s): Hydropower
River: Allai Khwar
Reservoir capacity: -
Construction Dates
Start of Project: 01/05
Start of RCC: 01/05
End of RCC: -/12
End of Project: 03/13
Specifications
Height: 51 metres
Length: 88 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|

Details
Country: Pakistan
Owner: Neelum Jhelum Hydropower Company
Type: Gravity
Purpose(s): Hydropower
River: Neelum
Reservoir capacity: 8 m3x106
Construction Dates
Start of Project: -/08
Start of RCC: -/08
End of RCC: 08/16
End of Project: 11/17
Specifications
Height: 47 metres
Length: 125 metres
Volume of RCC: -
Total volume: 156 m3x103
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| 154 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 51 | Ground-granulated blast-furnace slag |

Details
Country: Pakistan
Owner: WAPDA (Water and Power Development Authority) and MIRA Power Ltd. (a subsidiary of KOSEP)
Type: Gravity
Purpose(s): Hydropower
River: Poonch
Reservoir capacity: 22 m3x106
Construction Dates
Start of Project: 09/14
Start of RCC: 09/14
End of RCC: -/18
End of Project: 02/20
Specifications
Height: 35 metres
Length: 238 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|

Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates