Batang Toru
Download PDF data sheet
Batang Toru under construction

Particulars
Owner: PT. North Sumatra Hydro Energy
Designer: BIDHI
Contractor: SinoHydro Co. Ltd. (Construction Bureau Nº*)
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 18 m3x106
Height: 79 metres
Length: 137 metres
Volume of RCC: unknown
Total volume: 500 m3x103
Construction Dates
Start of Project: 10/21 (October 2021)
Start of RCC: 07/23 (July 2023)
End of RCC: 03/25 (March 2025)
End of Project: —/26 (— 2026)
Country: Indonesia
River: Batang Toru
DMS Co-ordinates: 1˚37'27.41"N, 99˚10'35.06"E
DD Co-ordinates: 1.624281, 99.176407