Hatta PSS-Saddle dam
Download PDF data sheet
Hatta PSS-Saddle dam completed

Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: unknown
Height: 38 metres
Length: 184 metres
Volume of RCC: 41 m3x103
Total volume: 45 m3x103
Construction Dates
Start of Project: 12/19 (December 2019)
Start of RCC: 03/21 (March 2021)
End of RCC: 09/21 (September 2021)
End of Project: —/24 (— 2024)
Country: UAE
River: unknown
DMS Co-ordinates: 24˚45'55.76"N, 56˚6'14.42"E
DD Co-ordinates: 24.76549, 56.104008
Facings
Upstream
| Slope | Type |
|---|---|
| RCC against precast concrete panels |
Downstream
| Slope | Type |
|---|---|
| RCC against precast concrete panels |
Spillway
| Slope | Type |
|---|---|
| RCC against precast concrete panels [stepped face] |
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
| 300 | 300 |
Cementitious material
| Cement (kg/m3) |
|---|
| 65 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 120 | Low-lime flyash (ASTM Class F) |