Karkheh (Pie Pol)

Download PDF data sheet
Karkheh (Pie Pol) completed
Karkheh (Pie Pol) completed

Particulars

Owner: Khozestan Province Power & Water Authority

Designer: Mahab Ghodss

Contractor: Jahan Kowsar Co

Statistics

Type: Gravity

Purpose(s): Flood Control / Hydropower

Reservoir capacity: 40 m3x106

Height: 34 metres

Length: 350 metres

Volume of RCC: 130 m3x103

Total volume: 270 m3x103

Construction Dates

Start of Project: 02/98 (February 1998)

Start of RCC: 07/99 (July 1999)

End of RCC: 07/00 (July 2000)

End of Project: /02 ( 2002)

Country: Iran

River: Karkeh

DMS Co-ordinates: 32˚29'21.86"N, 48˚07'8.81"E

DD Co-ordinates: 32.489407, 48.119114

Facings

Upstream

SlopeType
 Reinforced conventional concrete cast after RCC placement

Downstream

SlopeType
 Reinforced conventional concrete cast after RCC placement

Spillway

SlopeType
ogeeReinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
130
Pozzolan (kg/m3)Pozzolan Type
0No pozzolan used  -